7.65M TOP CHARGING COKE OVEN BATTERY OF SHANXI MEIJIN COKING PROJECT WAS COMMISSIONED

2020/12/08

  On December 15th, 2020, 7.65m top charging coke oven battery of Shanxi Meijin Coking Project was commissioned successfully. As a EPC contractor, ACRE’s scope is 4×70 batteries with chamber height 7.65m top charging, by product, CDQ, waste water treatment and utilities. This coke oven battery is the first 7.65m top charging coke oven in Shanxi Province, and also the third one in China. All the running 7.65m top charging coke ovens which are the largest top charging coke oven in China, are all designed by ACRE. The total coke capacity of Shanxi Meijin project is 3.85 MTPA. The advanced technology of 7.65m top charging coke oven help our client achieve first class level worldwide on equipment configuration, environment control and energy consumption.

  

  